July 25, 2025

July 2025 Construction Update

Construction Update

As we move into the next stage, the following updates highlight the current status and ongoing efforts:

  • Percentage of construction works being completed at end of June 2025 is 22.79%
  • Retention system and foundations complete
  • Civil works complete
  • Basement level 3 slab complete
  • Basement level 3 Pour 2 and basement level 2 Pour 1 is now complete, including precast panel erection to B3 with Formwork currently being erected for Basement Level 2 Pour 2.

Next Three Months

We expect to achieve several key milestones scheduled for completion in Q3 2025:

  • Concrete structure Level 2 suspended slab complete
  • Formwork and back propping stripped to basement levels 1, 2 & 3
  • Blockworks walls complete to basement levels 1, 2 & 3
  • Services Rough-In to Basement Levels 2 & 3 complete and services rough-in to basement level 1 underway.

We will keep sharing quarterly updates as construction advances.